Short answer: In England, requirement B3 of the Building Regulations 2010 requires buildings to inhibit internal fire spread, and Approved Document B explains how openings for pipes, ducts and cables in compartment walls and floors should be protected and fire-stopped. No rule covered here names a fire-stopping logbook, but regulation 38 and the Fire Safety Order make good records essential.

Which rules apply to fire-stopping in England?

In England, fire-stopping is shaped by the Building Regulations 2010 and Approved Document B during design and construction, regulation 38 at completion, and the Regulatory Reform (Fire Safety) Order 2005 once the building is in use. For higher-risk buildings, the Building Safety Act 2022 adds gateways and the golden thread.

You know the situation: the specification says "fire-stopping to comply with Part B", the M&E drawings show hundreds of penetrations, and nobody on site can say which document requires what, so every discussion starts from scratch.

RuleWhat it coversPhase
Building Regulations 2010, Schedule 1, requirement B3Internal fire spread, subdivision, concealed spacesDesign and construction
Approved Document BStatutory guidance on compartmentation, openings and fire-stoppingDesign and construction
Building Regulations 2010, regulation 38Fire safety information for the Responsible PersonCompletion
Fire Safety Order 2005, articles 9 and 17Risk assessment and maintenanceBuilding in use
Higher-Risk Buildings Procedures (England) Regulations 2023Gateways, golden thread, handoverHigher-risk buildings

Wales has its own versions of several of these rules, and Scotland and Northern Ireland have separate legislation, so this article covers England only.

What does requirement B3 say about internal fire spread?

Requirement B3 asks that the building keeps its stability in a fire for a reasonable period. Where reasonably necessary to inhibit fire spread, the building must be subdivided with fire-resisting construction, fitted with suitable automatic fire suppression, or both. It also requires that unseen spread of fire and smoke in concealed spaces is inhibited.

That matters for penetrations, because most end up above ceilings or inside risers. Regulation 7 adds that materials must be adequate, fixed so they perform as designed, and installed in a workmanlike manner.

What does Approved Document B say about penetrations through compartment walls and floors?

Approved Document B is the statutory guidance for meeting Part B in England. Volume 2 (buildings other than dwellings) has a section called Protection of openings and fire-stopping, and Volume 1 (dwellings) has its equivalent. Both cover openings for pipes, ventilation ducts and fire-stopping, so a penetration does not undermine the fire resistance of the wall or floor.

In practice, every opening is sealed with a suitable system, installed as tested, with a fire resistance (for example EI 60) matching the wall or floor, which depends on the use and height of the building.

From 2 September 2029, Approved Document B uses only the European classification in BS EN 13501 for fire resistance, with transitional arrangements, so recording the EN classification of each seal is a sensible habit.

What fire safety information must be handed over at completion?

In England, regulation 38 of the Building Regulations 2010 applies where the Fire Safety Order will cover the finished building. The person carrying out the work must give fire safety information about the building's design, construction, services and fire safety equipment to the Responsible Person no later than completion, or first occupation if that comes earlier.

A record of where each penetration sits and how it was sealed is a practical part of that information.

Who must maintain fire-stopping once the building is in use?

Under the Fire Safety Order, the Responsible Person maintains fire safety once the building is in use. Article 3 defines that person, usually the employer or whoever controls the premises. Article 9 requires a suitable and sufficient fire risk assessment, reviewed after significant changes. Article 17 requires a suitable system of maintenance for the premises and fire safety facilities.

In buildings with 2 or more sets of domestic premises, article 6 brings the structure and common parts within scope.

What changes for higher-risk buildings under the Building Safety Act 2022?

In England, a new building is higher-risk if it is at least 18 metres high or has at least 7 storeys, and either contains at least 2 residential units or is a hospital or care home. The Building Safety Regulator is building control for these buildings, and they cannot be occupied before passing its completion checks at gateway 3.

Under the Higher-Risk Buildings Procedures (England) Regulations 2023, the client keeps golden thread information electronically, accurate and up to date. At completion the client hands it, with the fire safety information, to the accountable person and the Responsible Person.

Is a fire-stopping logbook a legal requirement?

No rule covered here requires a document called a fire-stopping logbook. The law does require effective compartmentation, fire safety information at completion, maintenance once the building is in use and, for higher-risk buildings, an electronic golden thread. A logbook with a photo, location and product for each penetration is the most common way to show all of that.

Legally required in England?In practice
Fire-resisting subdivision where reasonably necessaryYes, requirement B3Basis of the fire strategy
Sealing penetrations to keep fire resistanceGuidance in Approved Document B to meet B3Work of the fire-stopping contractor
Fire safety information at completionYes, regulation 38Part of the handover file
Maintenance once in useYes, article 17 Fire Safety OrderFacilities management
Electronic golden threadYes, for higher-risk buildingsKept by the client, then handed over
Fire-stopping logbook by nameNot named in these rulesMost common way to show compliance

Installer certification such as FIRAS or BM TRADA Q-Mark, and guidance from the Association for Specialist Fire Protection (ASFP), are industry practice, not law. Ed Controls, project management and quality control software for construction, records each penetration as a ticket on the drawing, so that evidence exists before ceilings close.

Who is this explanation for?

This explanation is for people who need to link fire-stopping on site to the rules in England without reading all the legislation. It helps teams prepare for building control, handover and fire risk assessments, but does not replace a fire engineer or legal advice.

Suitable for:

  • Site, project and design managers who need to know which rules apply
  • Fire-stopping contractors linking their work to the regulations
  • Facilities managers and Responsible Persons after handover

Not intended as:

  • Legal advice, or a replacement for a fire engineer when designing fire compartments

Frequently asked questions

Does the Fire Safety Order apply to fire-stopping?
Yes, once the building is in use. The Responsible Person must keep the premises and fire safety facilities under a suitable system of maintenance and review the fire risk assessment after significant changes, such as a refurbishment that adds new penetrations through compartment walls or floors.

How many minutes of fire resistance does a fire-stopping seal need?
Requirement B3 does not set a single figure. Approved Document B links the required fire resistance of compartment walls and floors to the use and height of the building, and the sealed penetration must not reduce it. The seal's classification, for example EI 60, should therefore match the rating of the element it passes through.

Is third-party certification of fire-stopping installers mandatory?
No, the legislation covered here does not require it. Schemes such as FIRAS and the BM TRADA Q-Mark Fire Stopping Installation Scheme are voluntary, but many clients and principal contractors specify them in contracts because they give independent assurance that installers are competent and that seals are fitted as tested.

What counts as a higher-risk building in England?
For the design and construction phase, a higher-risk building is at least 18 metres high or has at least 7 storeys, and either contains at least 2 residential units or is a hospital or care home. The Building Safety Regulator is building control for these buildings and checks them at gateway 3 before occupation.

Is a fire-stopping logbook a legal requirement?
No rule covered here names a fire-stopping logbook. The Building Regulations, the Fire Safety Order and, for higher-risk buildings, the golden thread rules do require you to build, record and maintain compartmentation properly. A logbook with a photo, location and product for each penetration is the most practical way to show that.